Bellator Schedule Intelligence APIs implement deterministic schedule quality, validation, compliance, and simulation checks. Calculations and findings are derived from government publications, industry standards, guidelines, and recommended practices that define the expected properties of a healthy, well-formed schedule. This page identifies those sources, states how they inform the APIs, and points to the locations where readers can obtain the documents themselves.

The APIs do not replace a human reviewer’s judgment. They apply published criteria to a submitted schedule and return structured results. Thresholds and formulas are taken from the cited documents where those documents state them. Where a route uses its own threshold or weight, its description says so.

The NDIA Planning & Scheduling Excellence Guide (PASEG) is not one of those formula sources. Version 6.1 describes what a sound integrated master schedule looks like and how a program should use it. It does not state the thresholds or formulas these APIs calculate. It is on this page because that description is the reason the quality checks exist.

Endpoint cross-reference

The table below lists, for each production endpoint, what its response cites: metadata.standards_applied and the standard field on findings and score components. A value that is the route's own, such as a composite weight or a threshold that is not in the cited sentence, is labeled as the route's in the endpoint description. PASEG is not in this table.

Endpoint What the response cites
POST /api/v1/health/score The composite, its weights, and its grade bands are the route's; standards_applied is empty. Findings cite DCMA-EA PAM 200.1 §4.1 (missing logic) and §4.8 (high duration), and DECM 06A204b (isolated task). The structural component cites PAM 200.1 §4.1 and GAO-16-89G BP-2.
POST /api/v1/health/logic-audit DCMA-EA PAM 200.1 and GAO-16-89G BP-2. Findings cite PAM 200.1 §4.1 (missing logic), §4.2 (leads), §4.3 (lags), §4.4 (relationship types), §4.5 (hard constraints), and GAO BP-9 (out-of-sequence logic).
POST /api/v1/health/progress-audit DCMA-EA PAM 200.1 §4.9 (the actual-date half) and DECM 06A505a, 06A505b, and 06A506b, as the endpoint description states.
POST /api/v1/health/dcma-14-point DCMA-EA PAM 200.1 §4.1–§4.14. Each finding names its section.
POST /api/v1/health/dcma-decm DCMA EVMS Compliance Metrics v8.1 (selected schedule metrics).
POST /api/v1/health/planning-horizon Dimensions cite DCMA-EA PAM 200.1 §4.1, §4.8, and §4.10, and GAO-16-89G BP-2, BP-3, and BP-9. Weights and bands are the route's.
POST /api/v1/health/schedule-risk-index Components cite DCMA-EA PAM 200.1 §4.1–§4.5, §4.7, §4.9, §4.10, and §4.14, and GAO-16-89G BP-2, BP-3, BP-6, BP-7, BP-9, and BP-10. Weights are the route's.
POST /api/v1/analysis/validate GAO-16-89G BP-2 (predecessor loops, self-dependencies, and links to unknown tasks).
POST /api/v1/analysis/cpm The arithmetic is the route's. The description relates it to EIA-748E Guideline 6 and §2.6 and to GAO-16-89G practice 6.
POST /api/v1/analysis/resources DCMA-EA PAM 200.1 §4.10 (unresourced tasks) and GAO-16-89G BP-3 (over-allocation).
POST /api/v1/forensics/delay-analysis No standard. The three methods are the route's.
POST /api/v1/forensics/change-tracking No standard in the response. The description relates the categories to DECM 06A504a and 06A504b and to GAO-16-89G practice 10.
POST /api/v1/forensics/baseline-compare No standard in the response. The ratios, including BEI, are the route's; PAM 200.1 §3.1.2.4 defines BEI on the DCMA 14-point route.
POST /api/v1/forensics/as-planned-vs-as-built No standard. The variance classes and the critical-path overlay are the route's.
POST /api/v1/simulation/what-if GAO-16-89G BP-6. This is the critical-path calculation, not schedule risk analysis.
POST /api/v1/simulation/monte-carlo GAO-16-89G BP-8 (schedule risk analysis by statistical simulation). Default sampling is Latin hypercube (see Sandia SAND2001-0417).

Async counterparts (path + /async) use the same references as the synchronous route.

Referenced documents

DCMA-EA PAM 200.1 — EVMS Program Analysis Pamphlet (July 2012)

Defense Contract Management Agency pamphlet that defines the 14-point schedule assessment used in EVMS surveillance. Sections 4.1–4.14 state the individual measures and the thresholds or formulas associated with each.

POST /api/v1/health/dcma-14-point implements the 14-point assessment. The request profile identifier is dcma-pam-200.1.

A convenience copy is available at /standards/dcma-ea-pam-200-1-july-2012.pdf (releasability unlimited).

DCMA EVMS Compliance Metrics (DECM) — Tracker v8.1

The current set of 139 DCMA EVMS Compliance Metrics used in system surveillance and compliance reviews. Specification sheets define the test, numerator, denominator, and threshold for each metric.

POST /api/v1/health/dcma-decm implements selected schedule metrics from the v8.1 tracker.

Publication page: DCMA EVMS. Convenience copies of the v8.1 tracker, prioritization workbook, and specification sheets are hosted at /standards/.

GAO-16-89G — Schedule Assessment Guide (December 2015)

Government Accountability Office guide that defines ten best practices for developing and maintaining a reliable schedule, including logic, resources, critical path, float, schedule risk analysis, progress updates, and baseline control.

OpenAPI descriptions and finding metadata name GAO best practices where the calculation aligns with a practice. Schedule risk analysis practice is addressed by the simulation endpoints.

Product page: GAO-16-89G. HTML edition: Ten Best Practices.

Latin Hypercube Sampling — Helton & Davis, SAND2001-0417 (2002)

Public-domain Sandia National Laboratories report that describes Latin hypercube sampling (LHS) and its use for uncertainty propagation in complex systems. LHS is the default sampling method for POST /api/v1/simulation/monte-carlo. Independent Monte Carlo draws remain available via the method request field.

Report: Helton, J.C. and Davis, F.J. Latin Hypercube Sampling and the Propagation of Uncertainty in Analyses of Complex Systems. SAND2001-0417. Sandia National Laboratories, 2002. Unlimited release. Available via OSTI and Sandia technical report archives.

SAE EIA-748E — Earned Value Management Systems (revised February 2026)

SAE International information report that states the 27 guidelines for an earned value management system. Guideline 6 addresses scheduling authorized work and identifying task interdependencies.

Product page: SAE EIA748E. The document is copyrighted by SAE International.

NDIA IPMD EIA-748-E Intent Guide (14 May 2026)

National Defense Industrial Association guide that provides management value, intent, typical attributes, and objective evidence for each of the 27 EIA-748E guidelines. It is an interpretive aid, not the SAE standard.

Available from the NDIA IPMD guides page: Division Guides and Resources. Direct PDF: EIA-748-E Intent Guide.

NDIA IPMD Planning & Scheduling Excellence Guide (PASEG) — Version 6.1

Joint industry and government guide for building, using, and maintaining an integrated master schedule. Revised September 3, 2026. This is not the EIA-748 Intent Guide.

Version 6.1, section 1:

This guide provides the program management team, including new and experienced planners/schedulers, with practical approaches for building, using, and maintaining an Integrated Master Schedule (IMS).

Section 2 states eight Generally Accepted Scheduling Principles (GASP). The first five are the qualities of a valid schedule: complete, reasonable, and credible information based on realistic logic, durations, and dates. The other three describe a more mature schedule that is usable, resourced, and controlled. The guide says the principles are intentionally broad and do not specify particular methodologies. It also says a schedule that meets them is not merely healthy, but fit.

GASP Essential statement
1. Complete The schedule captures the entire discrete, authorized project effort from start through completion.
2. Traceable The schedule logic is horizontally & vertically integrated with cross-references to key documents & tools.
3. Transparent The schedule provides visibility to assure it is complete, traceable, has documented assumptions, & provides full disclosure of program status & forecast.
4. Statused The schedule has accurate progress through the status date.
5. Predictive The schedule provides meaningful critical paths & accurate forecasts for remaining work through program completion.
6. Usable The schedule is an indispensable tool for timely & effective management decisions & actions.
7. Resourced The schedule aligns with actual & projected resource availability.
8. Controlled The schedule is built, baselined, & maintained using a stable, repeatable, & documented process.

Section 10.1 defines the critical path as the continuous sequence of tasks which determines the program end date, and it distinguishes that path from near-critical paths and from driving paths to an interim milestone. The calculation it names is a forward pass for early dates, a backward pass for late dates, and total float as the difference between the early and late finish dates.

Section 10.2 is the schedule health assessment. It says periodic assessments are how a program checks that the IMS is valid for reporting and for predicting. The checks it lists include missing logic, open or dangling starts and finishes, leads, lags, relationship types, hard constraints such as Must Finish On and Must Start On, high float, negative float, high duration, invalid forecast dates, invalid actual dates, resource loading, tasks without a baseline, summary-task logic, planning packages still inside the detail-planning freeze period, out-of-sequence status, over-allocated resources, vertical traceability, and level-of-effort tasks driving discrete work. The same section says these metrics should be trigger points for analysis, not pass/fail gates, and that the guide does not provide thresholds. It also separates those health checks from execution metrics such as the Baseline Execution Index. The execution-metric chapters were not used as formulas.

Section 10.3.2 describes a schedule risk assessment: estimate how much schedule risk exists, where it is greatest, and the likely completion date, using risk, duration uncertainty, and merge points. It says the IMS, including logic, durations, constraints, and lags, should be validated before that assessment. That chapter is not the procedure behind POST /api/v1/simulation/monte-carlo.

Section 3.1 says to use a good schedule as a what-if analysis tool, to show how even small changes can have a large impact on future performance. That sentence is not a schedule risk assessment, and it is not the edit arithmetic behind POST /api/v1/simulation/what-if.

Quoted passages are from NDIA IPMD, Planning & Scheduling Excellence Guide, Version 6.1, September 3, 2026, sections 1, 2 (Figures 2-1 and 2-2), 3.1, 10.1, 10.2, and 10.3.2. Guides page: Division Guides and Resources. Direct PDF: PASEG v6.1.

Same concern, different calculation

The API calculation remains the document named in the endpoint table. PASEG is the chapter that discusses the same concern.

Endpoint What PASEG v6.1 discusses
POST /api/v1/health/score Sections 2 and 10.2. A health assessment asks whether the IMS is valid enough to report accomplishments and predict the remaining work. The guide does not define the score.
POST /api/v1/health/logic-audit Section 10.2. Missing predecessors or successors, open or dangling logic, relationship types, leads, and lags.
POST /api/v1/health/progress-audit Section 10.2. Invalid forecast dates, invalid actual dates, and out-of-sequence status. GASP 4 is accurate progress through the status date.
POST /api/v1/health/dcma-14-point Section 10.2 lists the same kinds of mechanical checks. It is not the 14-point procedure, and it does not state the pamphlet’s thresholds.
POST /api/v1/health/dcma-decm Not cited. PASEG is not the DECM tracker.
POST /api/v1/health/planning-horizon Section 10.2. High task duration, and planning packages that still need detail inside the freeze period.
POST /api/v1/health/schedule-risk-index Not section 10.3. That chapter is a probabilistic assessment. Section 10.2 treats health metrics as triggers for analysis, not as this composite index.
POST /api/v1/analysis/validate Section 10.2. Missing logic, and hard constraints such as Must Finish On and Must Start On.
POST /api/v1/analysis/cpm Section 10.1. Critical path, near-critical path, driving path, near-driving path, and the forward pass, backward pass, and total float.
POST /api/v1/analysis/resources GASP 7, and the section 10.2 rows for resource loading and over-allocated resources when loading is required. Section 6 was not used.
POST /api/v1/forensics/delay-analysis Not cited. No forensic method in the guide was opened.
POST /api/v1/forensics/change-tracking GASP 8 only: the schedule is baselined and maintained by a stable, repeatable, documented process. Section 9.2 was not opened.
POST /api/v1/forensics/baseline-compare GASP 8, and the section 10.2 check for tasks without baseline dates. Section 10.2 names the Baseline Execution Index as an execution metric, separate from the health checks. The section 10.4.4 write-up was not opened.
POST /api/v1/forensics/as-planned-vs-as-built Not cited. The statusing chapter was not opened.
POST /api/v1/simulation/what-if Section 3.1. Use a sound schedule to see the effect of a change. This is not the section 10.3 risk assessment.
POST /api/v1/simulation/monte-carlo Section 10.3.2 discusses a probabilistic assessment. That discussion is not the Monte Carlo procedure. The response cites GAO-16-89G BP-8.

Async counterparts use the same PASEG discussion as the synchronous route.

No endpoint cites an AACE recommended practice. Printed pages 2 through 4 of RP 57R-09 (Integrated Cost and Schedule Risk Analysis Using Risk Drivers and Monte Carlo Simulation of a CPM Model) were read; the practice says it is not a standard, and no route cites it. The other practices have not been read. See Governance.

Was this page helpful?

Your feedback helps us improve docs, reference pages, and Playground flows.

Topic: Standards · Page: /docs/standards

TermsPrivacyContact

Schedule analysis guidance. Not legal advice. You remain responsible for contract and agency compliance.