POST/api/v1/health/progress-audit

Progress Audit

Checks progress fields against status_date. Milestones (duration 0) are excluded by default. The integrity score starts at 100 and subtracts once for each severity that appears: critical 15, high 10, medium 5. It does not compute a DCMA percentage.

An actual start or actual finish after the status date is the actual-date half of PAM 200.1 section 4.9. That section also includes a forecast before the status date, and it states no percentage. Percent complete above 0 with no actual start, and percent complete of 100 with no actual finish, follow DECM 06A505a and 06A505b. Those rows use in-progress and complete tasks and allow up to 5 percent. This route uses percent complete and flags any row. A forecast finish before the status date on an incomplete task is part of DECM 06A506b (on or before the status date, count of zero). This route does not flag a forecast that falls on the status date. A forecast start before the actual start is this route's check. It is not 06A506c.

An actual start before a predecessor's actual finish is this route's out-of-sequence test. The 06A212a procedure was not quoted as that comparison, so the route does not cite it. A finish before its start is this route's date-order check. It is not section 4.9 and it is not 06A506a. The API reference page is the category table. The async route is the same audit.

DCMA-EA PAM 200.1DCMA EVMS Compliance Metrics v8.1

Progress audit

The OpenAPI description is the overview. This page is the category table.

status_date is required. Tasks with duration 0 are excluded by default. The integrity score starts at 100 and subtracts once for each severity that appears: critical 15, high 10, medium 5. It does not compute a DCMA percentage.

Category What the route counts Where the sentence is
Future actual actual_start or actual_finish after status_date PAM 200.1 §4.9. "Incomplete tasks that have a forecast start/finish date prior to the IMS status date, or has an actual start/finish date beyond the IMS status date are included in this metric." No percentage. The forecast half of that sentence is not this row.
Missing actual start percent_complete above 0 and no actual start DECM 06A505a is in-progress tasks with no actual start or with an actual finish, up to 5%. This route uses percent complete and flags any row.
Missing actual finish percent_complete of 100 and no actual finish DECM 06A505b is complete tasks with no actual finish, up to 5%. This route uses percent complete and flags any row.
Forecast finish before the status date Incomplete task, forecast_finish before status_date DECM 06A506b counts a forecast start or finish on or before the status date, and the threshold is a count of zero. This route does not flag a forecast that falls on the status date.
Forecast start before the actual start forecast_start before actual_start This route's check. It is not 06A506c. 06A506c is a forecast riding the status date across two months, up to 1%.
Out of sequence actual_start before a predecessor's actual_finish This route's comparison. The 06A212a sheet defines a count of out-of-sequence conditions and does not state this comparison on the standards page, so this row does not cite that id.
Finish before start Actual finish before actual start, or planned finish before planned start This route's date-order check. It is not §4.9 and it is not 06A506a. 06A506a is an actual date after the status date, up to 5%.

The async route is the same audit.

Request example

json
json
{
  "schedule_fixture": "string",
  "tasks": [
    {
      "duration_days": 10,
      "id": "T1",
      "name": "Design Phase",
      "percent_complete": 0,
      "planned_finish": "2026-01-15",
      "planned_start": "2026-01-01",
      "predecessors": [],
      "resource": "Team A"
    }
  ],
  "status_date": "2026-01-05",
  "options": {
    "exclude_milestones": true,
    "max_examples": 10,
    "include_recommendations": true
  }
}

Built from the request schema: field names and types, not a sample run.

Request fields from OpenAPI contract

Required fields and the optional fields that change this call are listed here. The shared task model stays on the task schema guide.

This table is generated from the endpoint schema in openapi.json.

FieldTypeRequiredDescription
options.exclude_milestonesbooleanOptionalExclude zero-duration tasks from progress checks.
options.max_examplesintegerOptionalMaximum anomaly examples to return per category.
options.include_recommendationsbooleanOptionalInclude recommended remediation steps.

Response example

json
json
{
  "status": "pass",
  "metadata": {
    "task_count": 0,
    "endpoint": "string"
  }
}

Built from the response schema: field names and types, not a sample run.

Response fields from OpenAPI contract

This table is generated from the endpoint response schema in openapi.json.

FieldTypeRequiredDescription
statusstringRequiredTop-level result status — always present in every response.
metadataobjectRequiredAudit trail and processing context — always present, never null.
metadata.task_countintegerRequiredNumber of tasks in the submitted schedule
metadata.endpointstringRequiredEndpoint path e.g. /api/v1/health/score

Schema

json-schema
{
  "$ref": "#/components/schemas/BellatorResponse_ProgressAuditData_"
}

Authentication

  • API key required

Reference details

Operation ID
health_progress_audit
Section
Health
Tags
Health
Playground link
/playground?endpoint=%2Fapi%2Fv1%2Fhealth%2Fprogress-audit&method=post

Was this page helpful?

Your feedback helps us improve docs, reference pages, and Playground flows.

Topic: Progress Audit · Page: /docs/api-reference/health_progress_audit

TermsPrivacyContact

Schedule analysis guidance. Not legal advice. You remain responsible for contract and agency compliance.