Progress audit
The OpenAPI description is the overview. This page is the category table.
status_date is required. Tasks with duration 0 are excluded by default. The integrity score starts at 100 and subtracts once for each severity that appears: critical 15, high 10, medium 5. It does not compute a DCMA percentage.
| Category | What the route counts | Where the sentence is |
|---|---|---|
| Future actual | actual_start or actual_finish after status_date |
PAM 200.1 §4.9. "Incomplete tasks that have a forecast start/finish date prior to the IMS status date, or has an actual start/finish date beyond the IMS status date are included in this metric." No percentage. The forecast half of that sentence is not this row. |
| Missing actual start | percent_complete above 0 and no actual start |
DECM 06A505a is in-progress tasks with no actual start or with an actual finish, up to 5%. This route uses percent complete and flags any row. |
| Missing actual finish | percent_complete of 100 and no actual finish |
DECM 06A505b is complete tasks with no actual finish, up to 5%. This route uses percent complete and flags any row. |
| Forecast finish before the status date | Incomplete task, forecast_finish before status_date |
DECM 06A506b counts a forecast start or finish on or before the status date, and the threshold is a count of zero. This route does not flag a forecast that falls on the status date. |
| Forecast start before the actual start | forecast_start before actual_start |
This route's check. It is not 06A506c. 06A506c is a forecast riding the status date across two months, up to 1%. |
| Out of sequence | actual_start before a predecessor's actual_finish |
This route's comparison. The 06A212a sheet defines a count of out-of-sequence conditions and does not state this comparison on the standards page, so this row does not cite that id. |
| Finish before start | Actual finish before actual start, or planned finish before planned start | This route's date-order check. It is not §4.9 and it is not 06A506a. 06A506a is an actual date after the status date, up to 5%. |
The async route is the same audit.