Logic audit
The OpenAPI description is the overview. This page is the rule table.
The score starts at 100. Each severity that is present is deducted once: critical 15, high 10, medium 5, low 2. The score is not below 0. A rule fails when its count is above zero. That pass line is this route's. PAM percentages are not applied here.
Grade: A at 90, B at 75, C at 60, D at 45, otherwise F.
| Rule | What is counted | Cited sentence |
|---|---|---|
| Missing predecessor | Tasks with no predecessor | PAM 200.1 §4.1. The pamphlet flags a share of incomplete tasks above 5%. This rule flags any count. |
| Missing successor | Tasks with no successor | Same section, same difference. |
| Isolated | No predecessor and no successor | Same section. |
| Leads | Negative lag | PAM 200.1 §4.2. "Leads should not be used; therefore, the goal for this metric is 0." |
| Hard constraints | SNLT, FNLT, MSO, MFO | PAM 200.1 §4.5. The pamphlet flags a share above 5%. This rule flags any count. SNET and FNET are not hard. |
| Dangling start | Predecessors exist and none constrain the start | DECM 06A204b, open starts or finishes. Tracker threshold is 0%. This route does not compute that ratio. |
| Dangling finish | Successors exist and none constrain the finish | Same metric. |
These rules are this route's. No document that was read states them, so the response does not name one:
| Rule | What is counted |
|---|---|
| Duplicate ids | Repeated task ids |
| Negative duration | Duration below 0 |
| Cycles | A dependency cycle |
| Invalid predecessor | A predecessor id that is not a task |
| Excessive lag | Lag above max_lag_days. The default is 5. Section 4.3 counts any positive lag as a share of logic links and flags above 5%. This rule is not that share. |
| Relationship types | Finish-to-start below 80%, start-to-start above 20%, finish-to-finish above 20%, or start-to-finish above 5%, unless the request sets other numbers. Section 4.4 says finish-to-start should be at least 90%. These defaults are not that sentence. |
| Out-of-sequence logic | The route's own sequence test. It is not PAM section 4.14. Section 4.14 is the baseline execution index. |
| Redundant links | A finish-to-start link with no positive lag that a chain of other finish-to-start links with no lead already implies. Only that chain says the successor starts after the predecessor finishes, so a path through a start-to-start or finish-to-finish link does not make the link redundant. |
The async route is the same audit.