Skip to content
POST/api/v1/health/dcma-decm

DCMA DECM Assessment

Runs the schedule metrics this route implements from the DCMA EVMS Compliance Metrics, tracker v8.1. The metric text is on the specification sheets. Where this route's default percentage differs from the tracker cell, the tracker cell is the standard and the default is this route's.

Defaults that do not match the v8.1 tracker: 06A205a fails above 5 percent here and the tracker allows up to 10 percent; 06A209a fails above 5 percent here and the tracker threshold is 0 percent; 06A501a fails above 0 percent here and the tracker allows up to 5 percent; 06A506c fails above 10 percent here and the tracker allows up to 1 percent; 08I101a and 10A303a fail above 0 percent here and the tracker allows up to 10 percent. 06A204b matches the tracker at 0 percent.

The route does not calculate the other metrics in the 139. It does not renumber the tests to the 27 guidelines in EIA-748E. The comparison is on the API reference page.

DCMA EVMS Compliance Metrics v8.1

DCMA DECM

The OpenAPI description is the overview. This page is the metric table for the checks this route runs. The standard is the v8.1 tracker cell. The specification sheet controls when a sheet and the tracker disagree. Those disagreements are in the source register, not repeated here.

The default profile, dcma-decm-default, uses the tracker threshold on every row except 06A401a. Each check reports where its number came from in threshold_source: decm-v8.1 for a tracker cell, bsi-default for 06A401a, the profile name when a profile changed it, and custom for an override in options.custom_thresholds.

"Tasks and milestones" below is every task that is not a summary. "Incomplete" is below 100% with no actual finish.

ID Tracker threshold How this route counts it
06A204b X/Y = 0%. Incomplete non-LOE tasks, activities, and milestones with an open start or finish. Matches.
06A205a X/Y ≤ 10%. Incomplete tasks, activities, and milestones with at least one lag. The denominator is tasks, not logic links. Matches: tasks with a positive lag on a predecessor link.
06A208a Summary tasks carrying logic. Any count fails.
06A209a X/Y = 0%. Hard constraints are SNLT, FNLT, Must Start On, and Must Finish On, plus the Open Plan and Primavera names on the v8.0 sheet. SNET and FNET are not on that list. Matches, over incomplete tasks and milestones.
06A210a LOE driving discrete work. Incomplete LOE with a non-LOE successor. Any count fails.
06A212a Out-of-sequence progress. Required when 06A204b trips. Any count fails. The condition is this route's reading: a started task whose finish-to-start predecessor has no actual finish, or whose start-to-start predecessor has no actual start, or that started before either date. Links to or from a summary, and links from an LOE, are not counted; 06A208a and 06A210a cover those.
06A401a A continuous critical path. Fails when no critical path is found. This is the route's own test, not the tracker's comparison of critical paths.
06A501a X/Y ≤ 5%. Tasks, activities, and milestones missing a baseline start or baseline finish. Matches.
06A504a, 06A504b Retroactive change to an actual start or actual finish. Up to 10%, against the latest schedule_history snapshot. Skipped without history.
06A505a An actual start with no actual finish, and percent complete between 0 and 100. X/Y ≤ 5%. In-progress tasks with no actual start, or with an actual finish, over in-progress tasks.
06A505b Complete tasks with no actual finish. X/Y ≤ 5%. Matches.
06A506a Actual start or actual finish after the status date. X/Y ≤ 5%. Over tasks with an actual start.
06A506b Forecast start or forecast finish on or before the status date. The threshold is a count of zero. Matches, over incomplete tasks. A started task's forecast start is not counted, because its start is an actual.
06A506c X/Y ≤ 1%. Forecast dates riding the status date. Riding means the forecast equals the status date now and equalled the latest snapshot's snapshot_date then. Skipped without schedule_history.
08I101a X/Y ≤ 10%. Summary-level planning packages with baseline duration of one day or less. Matches.
10A303a X/Y ≤ 10%. Planning packages with baseline duration of one day or less. Matches.

The score is checks passed over checks assessed. A skipped check is not counted, so a schedule sent without schedule_history is scored on 14 checks.

dcma-decm-strict sets every check to 0. An unknown threshold_profile, or a scope other than schedule_only, is a 422.

Tasks with no task_type can be classified with loe_task_ids, summary_task_ids, planning_package_task_ids and the other classification arrays, as on the DCMA 14-point route. A task's own task_type wins.

Rows without a tracker sentence in this table were not copied from the sheet onto this page. The identifier is the one the route returns. The other 139 minus these are not calculated.

Guideline numbers are still 01 through 32. EIA-748E's 27 guidelines are not this numbering.

The async route is the same assessment. It returns a job id instead of the checks.

Request example

json
json
{
  "schedule_fixture": "string",
  "tasks": [
    {
      "duration_days": 10,
      "id": "T1",
      "name": "Design Phase",
      "percent_complete": 0,
      "planned_finish": "2026-01-15",
      "planned_start": "2026-01-01",
      "predecessors": [],
      "resource": "Team A"
    }
  ],
  "status_date": "string",
  "target_finish_date": "string",
  "start_task_ids": [
    "string"
  ],
  "finish_task_ids": [
    "string"
  ],
  "schedule_history": [
    {
      "snapshot_date": "string"
    }
  ],
  "loe_task_ids": [
    "string"
  ],
  "apportioned_effort_task_ids": [
    "string"
  ],
  "schedule_margin_task_ids": [
    "string"
  ],
  "summary_task_ids": [
    "string"
  ],
  "planning_package_task_ids": [
    "string"
  ],
  "summary_level_pp_task_ids": [
    "string"
  ],
  "schedule_visibility_task_ids": [
    "string"
  ],
  "scope": "schedule_only",
  "options": {
    "threshold_profile": "dcma-decm-default",
    "custom_thresholds": {
      "check_06A204b_max_pct": 0,
      "check_06A205a_lags_max_pct": 0,
      "check_06A208a_max_pct": 0,
      "check_06A209a_constraints_max_pct": 0,
      "check_06A210a_max_pct": 0,
      "check_06A212a_max_pct": 0,
      "check_06A501a_max_pct": 0,
      "check_06A504a_max_pct": 0,
      "check_06A504b_max_pct": 0,
      "check_06A505a_max_pct": 0,
      "check_06A505b_max_pct": 0,
      "check_06A506a_max_pct": 0,
      "check_06A506b_max_pct": 0,
      "check_06A506c_max_pct": 0,
      "check_08I101a_max_pct": 0,
      "check_10A303a_max_pct": 0
    },
    "include_details": false
  }
}

Built from the request schema: field names and types, not a sample run.

Request fields from OpenAPI contract

Required fields and the optional fields that change this call are listed here. The shared task model stays on the task schema guide.

This table is generated from the endpoint schema in openapi.json.

FieldTypeRequiredDescription
status_datestring | nullOptionalProject status/data date (ISO 8601). Required for checks 06A212a, 06A506a/b/c. Skipped with informative message if absent.
target_finish_datestring | nullOptionalContract/target finish date (ISO 8601). Reserved for future Tier 3 use.
start_task_idsarray<string>OptionalTask IDs that legitimately have no predecessors (exempt from check 06A204b).
finish_task_idsarray<string>OptionalTask IDs that legitimately have no successors (exempt from check 06A204b).
schedule_historyarray<ScheduleHistorySnapshot>OptionalOptional historical snapshots for retroactive date change detection (checks 06A504a/b). Each snapshot requires snapshot_date + tasks.
schedule_history[].snapshot_datestringOptionalSnapshot date (ISO 8601)
schedule_history[].tasksarray<Task>OptionalTask list at snapshot time
schedule_history[].tasks[].idstringOptionalUnique task identifier
schedule_history[].tasks[].duration_daysnumberOptionalTask duration in days
schedule_history[].tasks[].predecessorsarray<string | DependencyLink>OptionalList of predecessor task IDs or dependency links. Supports: 'T1', 'T1FS+5 d', 'T2SS-2 d', or DependencyLink objects
schedule_history[].tasks[].namestring | nullOptionalTask name
schedule_history[].tasks[].resourcestring | nullOptionalResource assigned to task
schedule_history[].tasks[].resourcesarray<string>OptionalList of resources assigned (for multi-resource tasks)
schedule_history[].tasks[].percent_completenumberOptionalPercent complete (0-100)
schedule_history[].tasks[].physical_percent_completenumber | nullOptionalPhysical percent complete (0-100). Manual EVM entry by scheduler (MSP PhysicalPercentComplete). Authoritative for BCWP calculations. Captured separately from percent_complete on MSP imports.
schedule_history[].tasks[].planned_startstring | nullOptionalPlanned start date (ISO 8601)
schedule_history[].tasks[].planned_finishstring | nullOptionalPlanned finish date (ISO 8601)
schedule_history[].tasks[].actual_startstring | nullOptionalActual start date (ISO 8601)
schedule_history[].tasks[].actual_finishstring | nullOptionalActual finish date (ISO 8601)
schedule_history[].tasks[].baseline_startstring | nullOptionalBaseline start date (ISO 8601)
schedule_history[].tasks[].baseline_finishstring | nullOptionalBaseline finish date (ISO 8601)
schedule_history[].tasks[].constraint_typestring | nullOptionalConstraint type: ASAP, ALAP, SNET, SNLT, FNET, FNLT, MSO, MFO
schedule_history[].tasks[].constraint_datestring | nullOptionalConstraint date if applicable (ISO 8601)
schedule_history[].tasks[].task_typestring | nullOptionalTask type classification. Valid values: task (default), milestone, loe, summary, schedule_margin, planning_package, slpp, schedule_visibility. Drives which DCMA checks exclude the task.
schedule_history[].tasks[].wbs_codestring | nullOptionalWBS code (e.g., '1.2.3')
schedule_history[].tasks[].organization_codestring | nullOptionalOrg/dept identifier for anomaly categorization (Progress Audit)
schedule_history[].tasks[].custom_field_mapobject | nullOptionalAll WBS/OBS-pattern custom fields discovered in this MS Project file, keyed by alias (e.g., 'CWBS', 'OBS'). Null for XER imports or when no matching aliases exist.
schedule_history[].tasks[].forecast_startstring | nullOptionalCurrent forecast start date (ISO 8601)
schedule_history[].tasks[].forecast_finishstring | nullOptionalCurrent forecast finish date (ISO 8601)
schedule_history[].tasks[].total_float_daysnumber | nullOptionalPre-computed total float in days. Auto-computed by CPM if absent.
schedule_history[].tasks[].baseline_duration_daysnumber | nullOptionalBaseline duration in days. Auto-computed from baseline dates if absent.
schedule_history[].tasks[].delay_categorystring | nullOptionalDelay attribution category. Valid values: owner, contractor, design, procurement, weather, force_majeure.
schedule_history[].tasks[].earned_valuenumber | nullOptionalEarned Value (BCWP) in cost units. Requires options.include_ev_validation.
schedule_history[].tasks[].budgeted_costnumber | nullOptionalBudgeted Cost of Work Scheduled (BCWS) in cost units.
schedule_history[].tasks[].approval_requiredboolean | nullOptionalWhether this task requires explicit approval before it can start.
schedule_history[].tasks[].approval_statusstring | nullOptionalApproval workflow state. Valid values: not_required, pending, approved, rejected.
schedule_history[].tasks[].duration_distribution_typestring | integer | nullOptionalDuration distribution. None, Uniform, Triangular, Normal, Beta, or LogNormal.
schedule_history[].tasks[].duration_optimisticnumber | nullOptionalOptimistic duration, as days or a percent of duration_days.
schedule_history[].tasks[].duration_most_likelynumber | nullOptionalMost likely duration, as days or a percent of duration_days.
schedule_history[].tasks[].duration_pessimisticnumber | nullOptionalPessimistic duration, as days or a percent of duration_days.
schedule_history[].tasks[].duration_confidence_intervalnumber | nullOptionalConfidence interval percent, 50 through 100.
schedule_history[].tasks[].duration_estimate_unitstring | nullOptionalduration or percent_of_deterministic.
schedule_history[].tasks[].probability_of_existencenumber | nullOptionalChance the activity occurs, 0 through 100.
schedule_history[].tasks[].discrete_riskstring | nullOptionalRisk id this activity points at.
schedule_history[].tasks[].correlation_sourcesarray<string> | nullOptionalNamed correlation sources, same order as the coefficients.
schedule_history[].tasks[].correlation_coefficientsarray<number> | nullOptionalCorrelation to each source, percent from -100 through 100.
schedule_history[].tasks[].analysis_focal_itemboolean | nullOptionalMarks a sensitivity target.
schedule_history[].tasks[].calendar_idstring | nullOptionalCalendar whose lost-time model applies.
schedule_history[].tasks[].probabilistic_brancharray<ProbabilisticBranch> | nullOptionalMutually exclusive successors and their weights.
schedule_history[].tasks[].probabilistic_branch[].successor_idstring | nullOptionalSuccessor activity id.
schedule_history[].tasks[].probabilistic_branch[].probabilitynumber | nullOptionalWeight; 0 is never taken. Each trial picks one successor.
schedule_history[].tasks[].conditional_brancharray<ConditionalBranch> | nullOptionalSuccessors chosen from the predecessor finish.
schedule_history[].tasks[].conditional_branch[].successor_idstring | nullOptionalSuccessor activity id.
schedule_history[].tasks[].conditional_branch[].on_or_beforestring | nullOptionalISO date. The first row whose date is on or after the predecessor's finish in that trial is taken; null marks the else path.
loe_task_idsarray<string>OptionalLevel-of-effort task IDs, for tasks with no task_type.
apportioned_effort_task_idsarray<string>OptionalApportioned-effort task IDs, for tasks with no task_type.
schedule_margin_task_idsarray<string>OptionalSchedule margin task IDs, for tasks with no task_type.
summary_task_idsarray<string>OptionalSummary/rollup task IDs, for tasks with no task_type.
planning_package_task_idsarray<string>OptionalPlanning package task IDs (10A303a), for tasks with no task_type.
summary_level_pp_task_idsarray<string>OptionalSummary-level planning package IDs (08I101a), for tasks with no task_type.
schedule_visibility_task_idsarray<string>OptionalSchedule visibility task IDs, for tasks with no task_type.
scopestringOptional`schedule_only`: the 17 Tier 2 checks. Tier 3 scopes are not implemented; any other value is a 422.
optionsobjectOptionalRequest options for DCMA DECM assessment.
options.threshold_profilestringOptionalThreshold profile: `dcma-decm-default` (the DCMA EVMS Metrics Tracker v8.1 thresholds) or `dcma-decm-strict` (BSI's: every check at 0). Any other value is a 422.
options.custom_thresholdsDCMADECMCustomThresholds | nullOptionalPer-check threshold overrides (applied on top of selected profile).
options.custom_thresholds.check_06A204b_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_06A205a_lags_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_06A208a_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_06A209a_constraints_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_06A210a_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_06A212a_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_06A501a_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_06A504a_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_06A504b_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_06A505a_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_06A505b_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_06A506a_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_06A506b_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_06A506c_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_08I101a_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.custom_thresholds.check_10A303a_max_pctnumber | nullOptionalNo description in OpenAPI contract.
options.include_detailsbooleanOptionalInclude violating task IDs and detailed evidence objects in each check result.

Response example

json
json
{
  "status": "pass",
  "metadata": {
    "task_count": 0,
    "endpoint": "string"
  }
}

Built from the response schema: field names and types, not a sample run.

Response fields from OpenAPI contract

This table is generated from the endpoint response schema in openapi.json.

FieldTypeRequiredDescription
statusstringRequiredTop-level result status — always present in every response.
metadataobjectRequiredAudit trail and processing context — always present, never null.
metadata.task_countintegerRequiredNumber of tasks in the submitted schedule
metadata.endpointstringRequiredEndpoint path e.g. /api/v1/health/score

Schema

json-schema
{
  "$ref": "#/components/schemas/BellatorResponse_DCMADECMData_"
}

Authentication

  • API key required

Reference details

Operation ID
health_dcma_decm
Section
Health
Tags
Health
Playground link
/playground?endpoint=%2Fapi%2Fv1%2Fhealth%2Fdcma-decm&method=post

Was this page helpful?

Your feedback helps us improve docs, reference pages, and Playground flows.

Topic: DCMA DECM Assessment · Page: /docs/api-reference/health_dcma_decm

TermsPrivacyContact

Schedule analysis guidance. Not legal advice. You remain responsible for contract and agency compliance.