DCMA DECM
The OpenAPI description is the overview. This page is the metric table for the checks this route runs. The standard is the v8.1 tracker cell. The specification sheet controls when a sheet and the tracker disagree. Those disagreements are in the source register, not repeated here.
The default profile, dcma-decm-default, uses the tracker threshold on every row except 06A401a. Each check reports where its number came from in threshold_source: decm-v8.1 for a tracker cell, bsi-default for 06A401a, the profile name when a profile changed it, and custom for an override in options.custom_thresholds.
"Tasks and milestones" below is every task that is not a summary. "Incomplete" is below 100% with no actual finish.
| ID | Tracker threshold | How this route counts it |
|---|---|---|
| 06A204b | X/Y = 0%. Incomplete non-LOE tasks, activities, and milestones with an open start or finish. | Matches. |
| 06A205a | X/Y ≤ 10%. Incomplete tasks, activities, and milestones with at least one lag. The denominator is tasks, not logic links. | Matches: tasks with a positive lag on a predecessor link. |
| 06A208a | Summary tasks carrying logic. | Any count fails. |
| 06A209a | X/Y = 0%. Hard constraints are SNLT, FNLT, Must Start On, and Must Finish On, plus the Open Plan and Primavera names on the v8.0 sheet. SNET and FNET are not on that list. | Matches, over incomplete tasks and milestones. |
| 06A210a | LOE driving discrete work. | Incomplete LOE with a non-LOE successor. Any count fails. |
| 06A212a | Out-of-sequence progress. Required when 06A204b trips. | Any count fails. The condition is this route's reading: a started task whose finish-to-start predecessor has no actual finish, or whose start-to-start predecessor has no actual start, or that started before either date. Links to or from a summary, and links from an LOE, are not counted; 06A208a and 06A210a cover those. |
| 06A401a | A continuous critical path. | Fails when no critical path is found. This is the route's own test, not the tracker's comparison of critical paths. |
| 06A501a | X/Y ≤ 5%. Tasks, activities, and milestones missing a baseline start or baseline finish. | Matches. |
| 06A504a, 06A504b | Retroactive change to an actual start or actual finish. | Up to 10%, against the latest schedule_history snapshot. Skipped without history. |
| 06A505a | An actual start with no actual finish, and percent complete between 0 and 100. X/Y ≤ 5%. | In-progress tasks with no actual start, or with an actual finish, over in-progress tasks. |
| 06A505b | Complete tasks with no actual finish. X/Y ≤ 5%. | Matches. |
| 06A506a | Actual start or actual finish after the status date. X/Y ≤ 5%. | Over tasks with an actual start. |
| 06A506b | Forecast start or forecast finish on or before the status date. The threshold is a count of zero. | Matches, over incomplete tasks. A started task's forecast start is not counted, because its start is an actual. |
| 06A506c | X/Y ≤ 1%. Forecast dates riding the status date. | Riding means the forecast equals the status date now and equalled the latest snapshot's snapshot_date then. Skipped without schedule_history. |
| 08I101a | X/Y ≤ 10%. Summary-level planning packages with baseline duration of one day or less. | Matches. |
| 10A303a | X/Y ≤ 10%. Planning packages with baseline duration of one day or less. | Matches. |
The score is checks passed over checks assessed. A skipped check is not counted, so a schedule sent without schedule_history is scored on 14 checks.
dcma-decm-strict sets every check to 0. An unknown threshold_profile, or a scope other than schedule_only, is a 422.
Tasks with no task_type can be classified with loe_task_ids, summary_task_ids, planning_package_task_ids and the other classification arrays, as on the DCMA 14-point route. A task's own task_type wins.
Rows without a tracker sentence in this table were not copied from the sheet onto this page. The identifier is the one the route returns. The other 139 minus these are not calculated.
Guideline numbers are still 01 through 32. EIA-748E's 27 guidelines are not this numbering.
The async route is the same assessment. It returns a job id instead of the checks.