DCMA 14-Point
The OpenAPI description is the overview. This page is the check table. Quotations are from DCMA-EA PAM 200.1, July 2012. The default profile is dcma-pam-200.1. A caller can override any threshold value with options.custom_thresholds. An overridden value is the caller's, not the pamphlet's.
Section 4.0: "The identification of a red metric is not in and of itself synonymous with failure but rather an indicator or a catalyst to dig deeper."
Work tasks are every task except zero-duration tasks (milestones), level of effort, apportioned effort, schedule margin and summaries. A task is complete when it has an actual finish or is 100% complete. The checks count incomplete work tasks, or the links of incomplete tasks, as the pamphlet does.
| Check | What the route does by default | What the pamphlet says |
|---|---|---|
| 1 Logic | Incomplete work tasks missing a predecessor or a successor, fail above 5%. Declared start and finish tasks are exempt on their open side. | Section 4.1. Same population. "The number of tasks without predecessors and/or successors should not exceed 5%." |
| 2 Leads | Links of incomplete tasks with negative lag, fail above 0%. | Section 4.2. "Leads should not be used; therefore, the goal for this metric is 0." |
| 3 Lags | Links of incomplete tasks with positive lag, fail above 5%. | Section 4.3. "The number relationships with lags should not exceed 5%." The pamphlet omits the word "of"; the quotation keeps its text. |
| 4 Relationship types | Finish-to-start share of the links of incomplete tasks, fail below 90%. Start-to-finish links are counted and named; they do not fail the check on their own. | Section 4.4. Finish-to-start "should account for at least 90% of the relationship types." Start-to-finish "should only be used very rarely and with detailed justification." |
| 5 Hard constraints | MFO, MSO, SNLT, FNLT on incomplete work tasks, fail above 5%. | Section 4.5. Same four names. "The number of tasks with hard constraints should not exceed 5%." SNET and FNET are listed as soft. |
| 6 High float | Incomplete work tasks, critical ones included, with total float over 44 working days. Fail above 5%. | Section 4.6. "An incomplete task with total float greater than 44 working days (2 months) is counted in this metric." Flag above 5%. |
| 7 Negative float | Incomplete work tasks with total float below 0, fail above 0%. The 0% is BSI's (bsi-default). |
Section 4.7. "Ideally, there should not be any negative float in the schedule." No percentage is stated. |
| 8 High duration | Baseline duration over 44 working days, fail above 5%. Without a baseline the current duration is used and the message says so. | Section 4.8. Same 44 working days and the same 5%. The pamphlet also requires the baseline start to fall in the detail planning period or rolling wave. The request has no such boundary, so this route does not apply that filter. |
| 9 Invalid dates | An actual date after the status date, or an incomplete task forecast to start or finish before it. Each task counts once. Needs status_date. |
Section 4.9. "Incomplete tasks that have a forecast start/finish date prior to the IMS status date, or has an actual start/finish date beyond the IMS status date are included in this metric." "There should not be any invalid dates in the schedule." |
| 10 Resources | Incomplete work tasks with no resource, fail above 0%. The 0% is BSI's (bsi-default). |
Section 4.10. The pamphlet divides unassigned incomplete tasks by incomplete tasks if the schedule is resource-loaded. No percentage is stated. |
| 11 Missed tasks | Tasks with a baseline finish on or before the status date whose actual or forecast finish is later, over those due tasks. Fail above 5%. Skipped when no task has a baseline finish that is due. | Section 4.11. The denominator "does not include the number of tasks missing baseline start or finish dates." "The number of missed tasks should not exceed 5%." |
| 12 Critical path test | Slips the earliest incomplete critical task by 600 working days and passes when the project finish moves by the same amount. The 600 days is BSI's (bsi-default). |
Section 4.12. The test passes if the completion date shows "a revised Early Finish date that is in direct proportion … to the amount of intentional slip applied." |
| 13 CPLI | (critical path length + total float) / critical path length, in working days from status_date to the network's early finish, total float to target_finish_date. Fails below 0.95. Skipped without both dates. |
Section 4.13, pointing at 3.1.2.3. CPLI = (CPL + TF) / CPL. "A CPLI less than 0.95 should be considered a flag." |
| 14 BEI | All completed tasks / (tasks with a baseline finish on or before the status date + tasks missing a baseline finish). Fails below 0.95. | Section 4.14, pointing at 3.1.2.4. "Tasks missing baseline finish dates are included in the denominator." The pamphlet prints two procedures; this route uses the printed formula, not the eight-step spreadsheet count. |
The score is checks passed over checks assessed. Skipped checks are not counted. Each failed check is a finding whose affected_tasks lists the tasks the check counted; affected_task_ids on the check holds the same list.
threshold_source on each check says where its threshold value came from: dcma-pam-200.1 (the pamphlet's value), bsi-default (BSI's value where the pamphlet states none), the name of the profile that changed it, or custom (set in custom_thresholds). Profiles other than dcma-pam-200.1 are BSI threshold sets, not citations of GAO, AACE, or NASA. An unknown profile name is rejected with a 422.
The async route is the same assessment. It returns a job id instead of the checks.