Resource analysis
The OpenAPI description is the overview. This page is how coverage is counted.
Coverage
resource_coverage_pct is the share of work tasks with at least one resource in resources or resource. A work task has a duration above zero and is not a summary, level of effort, apportioned effort, or schedule margin. Milestones are not counted. None of these is work that needs resources.
dcma_check_10_compliant is true at 95% or more. The 95% is this route's line. DCMA-EA PAM 200.1 §4.10 states no threshold:
If the contractor does resource load their schedule, calculate the metric by dividing the number of incomplete tasks without dollars/hours assigned by the total number of incomplete tasks.
The section applies only when the schedule is resource-loaded: "The IMS DID (DI-MGMT-81650) does not require the contractor to load resources directly into the schedule." This route counts every work task, complete or not.
A schedule with no work tasks
When there are no work tasks, nothing is unresourced. dcma_check_10_assessed is false, and dcma_check_10_details reads "No work tasks to resource; DCMA #10 not assessed". dcma_check_10_compliant stays true and resource_coverage_pct stays 1.0, so existing clients still parse the response. Neither is a pass when dcma_check_10_assessed is false. The coverage gap in resource_risk_score is 0.
The async route is the same analysis.