Critical path
The OpenAPI description is the overview. This page is the arithmetic the route returns.
Relationship type and lag are applied. A plain task id is finish-to-start with lag 0.
| Quantity | Calculation |
|---|---|
| Early start | Maximum predecessor constraint, or 0 when there is no predecessor |
| Finish-to-start | Predecessor early finish + lag |
| Start-to-start | Predecessor early start + lag |
| Finish-to-finish | Predecessor early finish + lag − duration |
| Start-to-finish | Predecessor early start + lag − duration |
| Early finish | Early start + duration |
| Project duration | Maximum early finish |
| Late finish | Project duration when there is no successor. Otherwise the minimum successor constraint for the link type |
| Late start | Late finish − duration |
| Total float | Late start − early start |
| Critical | Total float is 0. The returned critical path is those task ids |
| Free float | Slack to the successor on the joining link. Total float when there is no successor |
| Criticality index | 1 when critical. Otherwise 1 − total float / the largest total float |
| Near-critical paths | Up to five start-to-finish paths whose minimum total float is positive, lowest float first. The zero-float path is not included |
| Calendar dates | Set when a planned, actual, or baseline start is present. project_finish_date and the per-task dates walk weekdays from the earliest of those starts. Saturday and Sunday are skipped. A finish date is the last day the task works: a 5-day task that starts Monday finishes that Friday. A zero-duration milestone falls on the day its predecessors finish. Lost-time calendars are not applied |
options.always_honor_constraints defaults to true. Must Start On sets early start to the constraint's weekday offset. Must Finish On sets early start so the finish lands on that offset. As Late As Possible is placed on its late start. When the flag is false, Must Start On and Must Finish On become Start No Earlier Than and Finish No Earlier Than, and Start No Later Than and Finish No Later Than are ignored. A constraint date is not applied when the schedule has no start date.
The relationship-type filter changes the network-detail counts. It does not remove links from the forward or backward pass.
What was read, and what it does not say
EIA-748E Guideline 6 (revised February 2026): "Schedule the authorized work in a manner that describes the sequence of work and identifies task interdependencies required to meet the requirements of the program."
EIA-748E section 2.6 defines a network schedule as the basis for critical path analysis. The definition does not state this procedure.
GAO-16-89G practice 6: "The schedule should identify the program's critical path—the path of longest duration through the sequence of activities."
This route's critical set is total float of 0, not a separate longest-path search.
DCMA-EA PAM 200.1 section 4.12 is an intentional-slip test. It is not this calculation. That test is POST /api/v1/health/dcma-14-point.
The async route queues the same calculation.